PROJECT PROFILE
Electric rate discounts to support electrification | Port of Long Beach, 2007-2015

Featured Image

E3, as electric rate consultant to the Port of Long Beach, the nation’s second-busiest port, led negotiations with Southern California Edison (SCE) to achieve electric rate discounts in recognition of the Port’s electrification program and resulting reductions in emissions of GHGs and criteria pollutants. Negotiations led to the California Public Utilities Commission’s March 2014 approval of SCE’s Rate Schedule ME, which provides electric rate discounts and a program under which SCE installs major electric infrastructure at no cost to the port or its tenants. These measures support critical electrification and environmental improvement projects at the Port, which is expected to quintuple its electric usage by 2030. The projects will improve air quality in the region, and rate discounts are expected to yield more than $300 million in savings over the term of the agreement.

Expertise areas

People


ALL E3 PROJECTS

Join us:

"(Required)" indicates required fields

This field is for validation purposes and should be left unchanged.

Connect with us:

E3